Column Rule - Baseline Task Planned Completion and Planned Completion

  • April 20, 2020
  • 1 reply
  • 946 views

I KNOW I've seen this somewhere (maybe a presentation at LEAP?) but I thought there is a way to do a Column rule where you could put in something like: When the Task>Planned Completion Date Greater than or Equal to Default Baseline Task >Planned Completion Date, show the field like - whatever you want (date in red, or similar). I thought there was a way to pull in the second data field instead of using a wildcard ($$TODAY) or a specific date.

I'm trying to get our team on board with using baselines, but I want to be able to show clearly when something has moved from the baseline using color coding.

Hopefully I'm not missing something obvious here.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

skyehansen
Community Advisor and Adobe Champion
April 20, 2020

This was in your 15 hacks session, but briefly involves putting FIELD: into that circled area and then saving the report and going back in to find another field picker on the right.

Level 3
April 20, 2020

Yes, that's it! I attended LEAP last year with my previous company and unfortunately didn't save out any of the presentation materials before moving over to Poly. Thanks for your quick response!

skyehansen
Community Advisor and Adobe Champion
April 20, 2020

no prob. You might want to also touch base with your AE to see if you can get access to some of those materials again, since you are a previous attendee.