Estimate at Completion Calculation

Avatar

Level 4

5/14/21

Currently Workfront calculates Estimate at completion by using the cost performance index and planned cost to estimate the the cost at completion. This method assumes that performance to date will match performance in the future.


I would like an additional EAC field that would assume that the remainder of the project will go according to plan.


EAC = Actual Cost to Date + Planned Cost Allocated for the future