Your achievements

Level 1

0% to

Level 2

Tip /
Sign in

Sign in to Community

to gain points, level up, and earn exciting badges like the new
Bedrock Mission!

Learn more

View all

Sign in to view all badges

Decrease workload on future weeks if the resource has work more hours than expected during one week.

Avatar

Level 1

05-05-2021

If a resource has a 20-hour task that must completed in two weeks, the Resource Planner splits the hours across the days of the two weeks. But what if the person can get more work done and completes 90% of his work in the first week? At this time the Resource planner continues to show 10 hours of pending work for the following week when it should only be 2 hours (10% of 20 hours). Showing 10 hours instead of 2, distorts the actual workload that a resource has for the next week and can show work that has already been done as pending.