Project Task Notification

  • September 3, 2020
  • 1 reply
  • 864 views

Hi Folks,

 

I have created task in project window and assign to user. When user updates the task by adding comment or mark as complete I should have receive notification for the same. But it seems that only one notification is delivered. Which is for initial task creation. 

Also configuration for Notify on update and notify on complete is enabled 

 

How can we receive update and complete notification too.

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Vijayalakshmi_S

Hi @khamat_bn,

Can you check if the OSGI component - com.day.cq.workflow.impl.email.TaskEMailNotificationService is active or it is in unsatisfied state. 

If it is unsatisfied, can you let know which service reference is unsatisfied. 

 

Notification should be in AEM Inbox or as an email if mail Id is configured for the assignee.

Please check the latter case + above OSGI component status and update this thread.

 

1 reply

Vijayalakshmi_S
Vijayalakshmi_SAccepted solution
September 4, 2020

Hi @khamat_bn,

Can you check if the OSGI component - com.day.cq.workflow.impl.email.TaskEMailNotificationService is active or it is in unsatisfied state. 

If it is unsatisfied, can you let know which service reference is unsatisfied. 

 

Notification should be in AEM Inbox or as an email if mail Id is configured for the assignee.

Please check the latter case + above OSGI component status and update this thread.