Has anyone found why regularly scheduled projects suddenly aren't delivered? Here are a couple issues that have arisen:

 

  • Issue 1: Daily Projects
    • 4 scheduled projects (PDF, CSVs for 2 different reports) have been sent consistently for the past 2.5 weeks without issue until this week
    • Failed to send 5/30/2022
    • Sent 5/31/2022
    • Failed to send 6/1/2022
    • Adjusted the delivery time from 6:00 am EDT to be an hour later in case our 6 am EDT time was too close to any Adobe "off-hour" maintenance windows; Sent on 6/2/2022
  • Use case 2: Monthly Projects - delivered on 1st day of month
    • Sent without issue for the past 10 months without any issues
    • 6/1/2022: 4 rescheduled from the daily to 7:01 am EDT were sent. 7 scheduled for 7:01-7:05 failed to send. Others sent as expected, with no rhyme or reason to which sent and which didn't. Small # of query ones for 7:01 failed to send, while one with many a larger # of queries for 7:03 did send. No special characters in sight. No email / server / policy changes of note.

Any ideas are welcome. We're tempted to change the delivery times, but not certain that will resolve issues (and not cause other issues).

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Jennifer_Dungan

I have logged a P2 Severity Ticket with Adobe... 

 

I also was having issue the same days as you... I suspect this has nothing to do with the schedule, and something was broken with a maintenance deployment a few days ago when the issue started.

 

 

Because of this, and the lack of information about what failed/what didn't... and no mechanism to bulk re-send... I logged the following idea: https://experienceleaguecommunities.adobe.com/t5/adobe-analytics-ideas/improvements-to-scheduled-project-area-more-info-about-last-next/idi-p/453949

 

Would love your thoughts on other things that could be added to improve this area so that when things do go south... there is a way to mediate it.. rather than spending all day finding the reports that were supposed to send, and sending them off manually.

 

 

1 reply

Jennifer_Dungan
Community Advisor and Adobe Champion
Jennifer_DunganCommunity Advisor and Adobe ChampionAccepted solution
Community Advisor and Adobe Champion
June 2, 2022

I have logged a P2 Severity Ticket with Adobe... 

 

I also was having issue the same days as you... I suspect this has nothing to do with the schedule, and something was broken with a maintenance deployment a few days ago when the issue started.

 

 

Because of this, and the lack of information about what failed/what didn't... and no mechanism to bulk re-send... I logged the following idea: https://experienceleaguecommunities.adobe.com/t5/adobe-analytics-ideas/improvements-to-scheduled-project-area-more-info-about-last-next/idi-p/453949

 

Would love your thoughts on other things that could be added to improve this area so that when things do go south... there is a way to mediate it.. rather than spending all day finding the reports that were supposed to send, and sending them off manually.

 

 

Level 2
June 2, 2022

@jennifer_dungan Thank you for validating this and for the great idea you suggested! Just liked it there. I’ll try to add the link to that idea to other forum posts I found today that would benefit.