Received scheduled report is not the last version

rosalbam4565918
Level 1
Level 1

I use report builder in Excell to send a scheduled report to my colleagues every monday at 6 am.

This report contains several sheets.

Last week, i've changed some segments and added 2 sheets, the saved my report.

Monday morning, in the report that was send to my colleagues : no new sheets, no new segment. It was still the old version.

Am I missing something ? Does anyone else have the same experience ? I presume it is a bug.

1 Accepted Solution
PratheepArunRaj
Correct answer by
Moderator
Moderator

Dear Rose,

The changes done will be in our Local Computer right? We should update so that Adobe Auto Scheduler will know the changes we have done!

No need to delete, just edit and reschedule the same task.

Thank You!

Arun

View solution in original post

3 Replies
PratheepArunRaj
Moderator
Moderator

Dear rosalbam45659182

Just Saving the report wont work. After saving the report, you need to select the updated report and reschedule it.

Thank You!

Arun

rosalbam4565918
Level 1
Level 1

Do you mean that i have to delete my schedule of report first ?

I don't find this procedure very userfriendly.

PratheepArunRaj
Correct answer by
Moderator
Moderator

Dear Rose,

The changes done will be in our Local Computer right? We should update so that Adobe Auto Scheduler will know the changes we have done!

No need to delete, just edit and reschedule the same task.

Thank You!

Arun