Organization With Different Definitions of "Week" | Community
Skip to main content
Level 2
May 24, 2022
Solved

Organization With Different Definitions of "Week"

  • May 24, 2022
  • 2 replies
  • 1698 views

Hi!

 

I work for a large organization that operates in many different countries. Some markets define "week" as Mon - Sun while others define it as Sun - Sat. What is the best way to set up/organize my report suites to account for both of these week definitions for each market

 

For example, our UK report suite is set up to define weeks as Mon - Sun by default. However, I am in the US and would like to have the ability to view weekly UK data using Sun - Sat weeks. 

 

Would multiple virtual report suites for each country be a possible solution?

 

Thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by yuhuisg

Unfortunately for your case, calendar weeks are defined at the report suite level. Even with Virtual Report Suites, you're stuck with the calendar week configuration of the original report suite.

2 replies

yuhuisg
Community Advisor
yuhuisgCommunity AdvisorAccepted solution
Community Advisor
May 25, 2022

Unfortunately for your case, calendar weeks are defined at the report suite level. Even with Virtual Report Suites, you're stuck with the calendar week configuration of the original report suite.

tsherwiAuthor
Level 2
May 25, 2022

That's what I was afraid of. Thanks for your response.

Alexis_Cazes_
Level 10
May 26, 2022

Why is instance not working ? If you apply the evar instance metric and not Occurences (which is different) it should return you data only when eVar value was physically set in the analytics hit

yuhuisg
Community Advisor
Community Advisor
May 26, 2022

@alexis_cazes_ Did you answer in the wrong thread?

Alexis_Cazes_
Level 10
May 26, 2022

yep sorry