Hi Team, 

 

We have a requirement of moving bulk offers around ~2k offers from Stage / Dev enviorment to PROD.

When I tried moving a sample one from existing stage environment to Dev box ; what i noticed is the offer that I took was approved and was published in Live environment. 

 

So, if we move this offer (which is in design environment)  from stage to Dev, it will again ask for the approvals and I assume post approval the offers gets published to Live environment. 

 

Since we have around 2K offers approving each manually is a tedious job, so wanted some inputs, should it be ok if we move the Live offer package or is there any other better way to do the bulk movement of offers from one environment to another. 

 

Thanks,
Adithya

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Jonathon_wodnicki

Hi,

 

Use mass update to mark everything approved (there are 4 fields for approval in offers?), then publish per usual.

 

Thanks,

-Jon

1 reply

Jonathon_wodnicki
Community Advisor
Jonathon_wodnickiCommunity AdvisorAccepted solution
Community Advisor
October 7, 2020

Hi,

 

Use mass update to mark everything approved (there are 4 fields for approval in offers?), then publish per usual.

 

Thanks,

-Jon

adithyacs86
Level 5
October 19, 2020

Hi Jon,

Yes this worked for me.. thanks for the suggestions. 

 