Remove Commit Date

  • February 5, 2025
  • 1 reply
  • 316 views

Anyone been able to figure out how to remove/delete/change commit dates using Fusion. WF has/had an annoying habit of setting the commit date to the planned CPL date when a user self-assigns themselves to a task and it's PITA to clean up.......

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Pan_Shahbazian

You can't set it to 'null,' but you can replace it with another date. If you set it to null, it'll just keep the original commit date. 

1 reply

Pan_Shahbazian
Pan_ShahbazianAccepted solution
Level 2
February 6, 2025

You can't set it to 'null,' but you can replace it with another date. If you set it to null, it'll just keep the original commit date.