How to Create an Issue Directly Under a Task Instead of a Project?

  • October 10, 2025
  • 2 の返信
  • 401 ビュー

Hello Community,

I’m trying to create an issue under a specific task (see image below). However, the issue always gets created directly under the project instead of the task, resulting in a structure like:
Project >> Issue Name
instead of
Project >> Task >> Issue Name

I can move it afterward using Misc Action >> moveToTask, but I’d like to know if there’s a way to create it under the task directly in one step. Any guidance would be appreciated!

このトピックへの返信は締め切られました。
ベストアンサー AndrewShevchyk

Hello,
You need to change Source Task ID to Source Object ID and add one more field Source Object Type = TASK, like this:

 

 

2 の返信

Level 5
October 10, 2025

Hello,

 

I have similar set up as well but the modules prior are watch or search > read > then create the issue and map to the fields from the previous modules.

 

I'm not sure if this is the best way but it works for me. 

 

=D

Level 2
October 12, 2025

Hello,
You need to change Source Task ID to Source Object ID and add one more field Source Object Type = TASK, like this:

 

 

_Manish_Singh
_Manish_Singh作成者
Level 9
October 13, 2025

Thank you for the solution.