Skip to main content
_Manish_Singh
Level 9
Jun 4, 2024 12:40 PM UTC
Question

Assign Timesheet Approver

Hello - I was testing timesheet creation using Fusion. It creates the timesheet and sets the start/end date correctly, but it didn't assign the approver, it was empty. What is the right way to assign an approver?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

_Manish_Singh
Level 9
Jun 4, 2024 2:54 PM UTC

As the direct mapping was not working, I used custom API call and it worked.

Translate
Level 5
Jun 5, 2024 5:25 PM UTC

File a support ticket with Adobe if you feel there's a problem with the Fusion widget.  (The forums here aren't support tickets, so formal response is less guaranteed.)

Translate