Question

Workload Balancer for Fallen Behind Projects

  • July 9, 2025
  • 1 reply
  • 255 views

Hello! When using the Workload Balancer, you can see everyone's projects that they have been assigned to. If a project has fallen behind, for example, a designer (role) has a task that was planned to be completed two weeks ago, that task does not appear on the WLB for the current week. Is there a way to know/see tasks (of e.g. designers) for fallen behind projects for the current week? -- so that when we go assigned new tasks for designers, we can take into account fallen behind projects. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

BridgettePr1
Level 2
July 10, 2025

This may or not be helpful, but I created a custom report that shows all of the users on my team (grouped by: assigned to), project name task name, the % complete on each, and how many days past the due date (if applicable) each task is. I know it's not as quick to get to as workload balancer, but you can add and remove as much detail you want from creating a custom report. 

 

Columns- Can Start, Project Name, Task Name, Assignments, Duration, Pln Hours, Start On, Due On, % Complete, Days Late