Question

Why would my due dates be different on two projects with the same start date, task constraints, and duration type?

  • August 14, 2020
  • 3 replies
  • 605 views
No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

Level 2
August 17, 2020

‚Check the Project Owners and the project settings to see if you have incorporated Weekends / Holidays in the set up.

Level 4
August 17, 2020

It is possible that an assignee is on holiday, as registered in the Workfront calendar, and that therefore the planned end date of the task has been pushed further.

DeniseMoore
Level 4
August 17, 2020

The above two comments are true and also IF the planned hours and/or planned start TIME isn't the same on all on both project or the tasks within them, it could throw off the planned completion date.