Hi. I'm looking for direction on how to create a utilization report. We are a creative services team made up of project managers, writers, editors, designers and myself, production. We are not a revenue generating business unit. However, we produce over 2,000 projects per year (print, digital, editing only, etc.).
Utilization is extremely important to us.
The utilization report needs to show utilization of an individual, by Role. And, utilization of each of our teams (writing, editing, design, production and project management).
The utilization report would be generated at the end of each month.
Our "old" system would produce a utilization report based on the “formula” of (per sample attached)
Total Working Days for 2016 = 261 x 8 hours per day = 2,088 hours per year
Calculation is total project hours worked per month, divided by total monthly hours, minus PTO taken.
Any thoughts on how to produce a report based on the above? OR, any suggestions how to better capture utilization are welcome.