To get only my child tasks why do you Select Equal "0" for the number of children - wouldn't it be not equal

  • October 23, 2020
  • 4 답변들
  • 1525 조회

Apply a parent task filter using the report builder, Go to the Reports area in your Global Navigation Bar, Click New Report,

Select a Task Report, Click Filters, Click Add a Filter Rule, select Number of Child equal "0"

이 주제는 답변이 닫혔습니다.

4 답변

imgrund
Adobe Employee
Adobe Employee
October 23, 2020

Hi - tasks do not have any subtasks have "0 children". If you put the filter does not equal 0, you would get tasks that have subtasks on them because 1, 2, 3, etc. do not equal 0.

Not sure if that helps, but thought I'd share. ;)

imgrund
Adobe Employee
Adobe Employee
October 23, 2020

I think it is more confused working of the bolded text since it says "parent task filter". But if you look just before the bold text, it says:

You can apply the following task filter to display only working tasks and remove all parent tasks.

Working tasks are tasks that can be worked independently and are not parent tasks to other tasks.

To remove all parent tasks, you need Number of Children equals 0. That way you are show tasks that do not have subtasks. (i.e. tasks that are not parents)

Community Advisor
October 23, 2020

Hi Kathleen,

By definitiion, a parent task must have children (or 'sub-tasks) for it to be a parent. So by selecting number of children = 0, you are specifying that it is not a parent. If you were to select number of children does not equal 0, this would mean that the task had 1 or more children which would make it a parent.

Another way of achieving the same outcome would be to add a filter rule stating that Task > Parent ID is not blank. All child tasks have a parent associated with them, which means that there must be a parent ID for it to be a child task.

Best Regards,

RIch.

imgrund
Adobe Employee
Adobe Employee
October 23, 2020

Hi - jumping in, this one is not quite right.

Example:

Kick-off

Phase 1

Task 1

Task 2

Phase 2

Task 3

Task 4

Launch!

If I did the report with "Parent ID is not Blank", only Task 1, Task 2, Task 3, and Task 4 would show up.

If I did the report with Number of Children equals 0, I'd get back Kick-Off, Task 1, Task 2, Task 3, Task 4, and Launch.

Community Advisor
October 23, 2020

Thanks Anthony,

Definitley worth highlighting the differences between the two filter options as they do produce different results. I guess it depends on what you want your report to achieve. In your example Kick-Off and Launch are not child tasks (as they have no parent), so you may or may not want to include them in the report.

Kick-off - TASK

Phase 1 - PARENT

Task 1 - CHILD

Task 2 - CHILD

Phase 2 - PARENT

Task 3 - CHILD

Task 4 - CHILD

Launch! - TASK

KathleenKSJH작성자
Level 2
October 23, 2020

Thank you everyone!

kynabaker16
Adobe Employee
Adobe Employee
October 26, 2020

Hi all,

Just wanted to let you know that I sent this thread to our documentation team and we've updated the article to hopefully be a bit clearer for those searching the next time around. Thank you for raising this and if you have any edits you'd like to suggest on a documentation article you can always "Send feedback" directly from the page as well!

Have a great day!

Kyna

KathleenKSJH작성자
Level 2
October 26, 2020
Thank you!