Hi all, We are trying to create a report for a manager that contains a link to each of his team's timesheet for the week. There doesn't seem to be an out-of-the-box solution for a field like that in a Timesheet report. Anyone had any luck with this? Thanks! CC: @Nick Matarazzo Alison Angilletta RWJBarnabas Health
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

Level 6
February 13, 2019
Hi @Alison Angilletta I have just run a timesheet report and included the field date range and this seems to appear in the report as a hyperlink and if you click on it takes you straight to that timesheet. Does this work for you? Vicky Fitzgerald Telegraph Media Group Limited
AlisonAn5Author
Level 3
February 13, 2019
That is exactly what we are looking for, but I didn't have that field when I tried to add it to an existing timesheet report. However, I just created a new timesheet and it was one of the fields included. It must be a field WF builds the text mode for you, but doesn't have a discrete field for. Either way, problem solved! Thanks! Alison Angilletta RWJBarnabas Health
Level 6
February 14, 2019
Ahh at least its solved now! Glad to have helped :) Vicky Fitzgerald Telegraph Media Group Limited