Text mode Help for "Current Task" view column

  • November 18, 2025
  • 1 reply
  • 128 views

I'm trying to have a column at my Program level and Project level to show me what task we are on, who it's assigned to and the due date. I started with the text mode below but it's not working for me. Anyone ideas what I have wrong here? 

 

 

displayname=Current Task

listdelimiter=<div> listmethod=nested(tasks).lists textmode=true type=iterate usewidths=true

valueexpression=IF({numberOfChildren}=0,IF({canStart},IF(CONTAINS("CPL",{status}),"",CONCAT({name}," - ",{assignedTo}.{name}," - ",{plannedCompletionDate}))))

valueformat=HTML width=400

Best answer by Kim_Hodnett

That's it - Thank you!!!

1 reply

IvanBebek-iX
Level 5
November 19, 2025

Hi @kim_hodnett,

 

I have refactored this a bit, added new lines, removed some extra spaces and it works normally/as intended I would say. Could you please try this

 

displayname=Current Task listdelimiter=<div> listmethod=nested(tasks).lists type=iterate usewidths=true valueexpression=IF({numberOfChildren}=0,IF({canStart},IF(CONTAINS("CPL",{status}),"",CONCAT({name}," - ",{assignedTo}.{name}," - ",{plannedCompletionDate})))) valueformat=HTML width=400

 

Please let me know if it works now. 

 

Best regards,
Ivan

Kim_HodnettAuthorAccepted solution
New Member
November 19, 2025

That's it - Thank you!!!

IvanBebek-iX
Level 5
November 20, 2025

Hi @kim_hodnett ,

 

Could you also mark this as correct, so its helps community with finding the solution in the future. Thank you in advance, appreciate it.

 