Question
Task Start Date defaults to project start date when adding from Dynamic Board
Hi everyone,
We are currently having an issue with our dynamic boards where when we add a card from the board view, it defaults the date to the project start date. It will default it even if we have the date correct when we input the card - when we refresh it refreshes the date to the project start date. Obviously this is an issue.
Has any one had a similar issue? If so, how did you fix it?
Thanks!
Sabrina