task predecessor advice
Hi All,
I need to make a tweak to a project schedule I was given. The original schedule has my team's task (task 27) with a basic Finish-Start predecessor of the task before it (task 26):

However, after some clarification, I've learned that task 27 (a) can begin after task 24 is complete; and (b) will require additional work (taking the planned 5-day duration) after task 26 is complete. I'm playing around with two possible predecessor scenarios, and I wanted to see what others would recommend.
Scenario 1: use a Scheduled-Start dependency for the task 26 predecessor (this keeps the schedule dates the same, but task 27 does not get marked as Can Start when task 24 is completed):

Scenario 2: use a Finish-Finish dependency for the task 26 predecessor and add a lag of 5 days (this marks task 27 as Can Start when task 24 is completed, but the schedule dates change slightly):

I'm curious as to what approach others use for similar setups.
Thanks.