Task now ready to start notification when predecessor is in a different project
I need the assignee to a task to receive a Task now ready to start notification for a task that has a predecessor in a different project. When i tested the notification was only sent if the predecessor was in the same project. Is there a way to get this to work? Or, is there another way for the assignee to this task to be informed when the task in the other project is completed?
