Task Level to Project Level Field/Calculation?
Hello! I am trying to create a calculated Project level field that pulls/calculates a number based on a task level field. I know when I've done the opposite i do, Project.Field Name.. Is it possible the opposite? I want my project level field to take the numbers I've entered into the task field and sum together, just not getting anywhere.
Project Field - Total Additional Days = 8
Task 1 Additional Days = 5
Task 2 Additional Days = 3