spencer_w
Level 2
December 3, 2024
Question

Task highlights for time off

  • December 3, 2024
  • 1 reply
  • 426 views

Is there a way to visually indicate tasks that are affected by user's time off in the project view? An icon, a row highlight, etc. Anything would be helpful.

 

Right now it's too easy to miss project delays because individual task rows don't provide any indicator that they're affected. 

 

I tried experimenting with project view conditionals, but didn't see any attribute that would capture this. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Kurt_Jones
Community Advisor and Adobe Champion
Community Advisor and Adobe Champion
December 4, 2024

spencer_w,

There is a field available called Has Time Off, which you can find under the Assigned To field if you search that might help you.  I tested by assigning myself to a task with planned completion date of 12/15.  I went into the project view (any view), selected the Planned Completion Date field then did a conditional where Assigned To Has Time Off is equal to true. Then make that Planned Completion Date background red.  I went to my time off calendar and set time off for 12/15.  Lo and behold when viewing that project and that assignment for me on 12/15 task the planned completion date field was red.  I that is what you were looking for.  Of course, folks have to be good about inputting their time off schedule or this becomes moot (an issue we have).

If my response answered your question, please mark it answered, so others can find the answer