Task Duration Calculation
Hi all,
I'm having difficulty with WF tasks calculating the durations I need.
For example, when I set a task duration of 1 Month: WF calculates it from 4/1/20 to 4/23/20...which is only 17 business days, when I need it to be closer to 20 or 21 (5 working days per wk).
And when I plan even longer tasks, it skews dates even more.
For example, when I set 3 months: WF calculates it from 4/1/20 to 6/9/20..but I'd need it to be closer to the beginning of July.
The calendar I'm using is scheduled from 8-6 M-F, so I'm not sure if this is impacting this but I'm really just trying to get it closer to actual dates because as you can see from the 3mo scenario, timing would be off close to about 3wks which isn't good!
Thanks for your help!