Seeing $0 in planned labor costs on templates and projects

  • June 5, 2024
  • 1 respuesta
  • 832 visualizaciones

Has anyone seen where a template task has an assignment and planned hours and the planned labor cost is at a $0 even if the assignee has a job role with a cost per hour? It is also not consistent some tasks with the same assignee do have a cost. 

Este tema ha sido cerrado para respuestas.
Mejor respuesta de skyehansen

there's a setting on every task called "Cost Type". Is it possible that some of your tasks have "no cost" as the cost type?

1 respuesta

skyehansen
Community Advisor
skyehansenCommunity AdvisorRespuesta
June 6, 2024

there's a setting on every task called "Cost Type". Is it possible that some of your tasks have "no cost" as the cost type?

Level 3
June 6, 2024

Oh thank you! I thought I was going crazy