It appears you can only assign one scorecard to a project but I have a use case where we have one scorecard that asks a series of 26 questions that determine a project complexity score and another scorecard that asks 9 questions to determine project priority. Does anyone have a workaround other then combining both scorecards into one? Bryan Edgerton ISD Project Manager Secretary of State Agency
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

October 31, 2017
Bryan, We usually use a number of custom forms and questions to do just what you're asking. You can use calculated fields to do even more calculations that would otherwise not be possible. Have you looked into the custom form areas to do staged or more complex/fluid evaluations? Ryan Eaton Workfront