*SCHEDULES in Workfront* - Assigned a schedule to a project with exception dates blocked out, project is not recalculating schedule!
Someone created a project schedule, then asked for specific dates to be blocked out that are different to our default schedule in Workfront. I created a custom schedule with different dates blocked out as exception dates, and assigned it to that project. The project is not recalculating the schedule based on that calendar. (Meaning, even though the calendar schedule I created has dates of 12/18-1/9 blocked off as full exception dates, the project schedule is still telling me certain task due dates are falling within that window of time). Is there a trick to this I am missing? Thank you - Olivia