Question
Schedule from start versus completion date question
Hi, Looking for some help on the easiest way to fix the planned start and completion dates of a large project. The 2018 version of the project was copied and used to build the 2019 version of the project because the majority of the tasks are the same. Just 2019 dates instead of 2018 basically. However, I just learned the original planned start date of 2018 has transferred over to the 2019 version. Even though all of the tasks have been updated and built out correctly for 2019. I need the planned start to be 2019. I am scared to just change it bc it could impact the task dates. I was thinking to copy the project and remove all of the tasks. Set the start date correctly and then move the tasks over from the previous project. Thanks! Peter Mitchell Prudential Financial -Business Performance Solutions