Resource Planner and Capacity
What do you all use as your percent for resource capacity? For example - a person works 40 hours a week - currently we have them listed as available for 37.5 hours a week. Some of our employees say they heard in a training class that we should be listing available hours at 80% which would be 32 hours a week available. Help! What do you all do? We are an advertising print/digital/video/marketing area. Thanks! Lauren McCollim, M.B.A, PMP Advertising Project Manager Pensacola Christian College