Reporting on tasks that do not have cross project predecessors

  • October 24, 2022
  • 1 reply
  • 514 views

There was a post that answered my question from 2017 but it is garbled on my screen, and I wonder if anybody can translate the text mode code needed to add a filter that removes tasks that have a cross project predecessor (in a task report)?

 

https://experienceleaguecommunities.adobe.com/t5/workfront-questions/want-a-report-that-shows-all-tasks-without-predecessor/m-p/496799#M28549

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by William

Hi Jill. 

I believe this is the filter you are asking for:

EXISTS:a:$$EXISTSMOD=NOTEXISTS
EXISTS:a:$$OBJCODE=PRED
EXISTS:a:isCP=true
EXISTS:a:successorID=FIELD:ID

1 reply

William
Community Advisor
WilliamCommunity AdvisorAccepted solution
Community Advisor
October 24, 2022

Hi Jill. 

I believe this is the filter you are asking for:

EXISTS:a:$$EXISTSMOD=NOTEXISTS
EXISTS:a:$$OBJCODE=PRED
EXISTS:a:isCP=true
EXISTS:a:successorID=FIELD:ID