Reporting Hours Logged under each Status

  • October 26, 2022
  • 1 reply
  • 548 views

I am trying to create a report which will show me the total number of hours logged under each status our projects progress through. Ex. Project A logged 3 hours under scoping status and 10 hours in active status. Through my attempts, it seems I can only get the report to show the total hours of projects with a specific status. Any ideas or recommendations would be appreciated. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Doug_Den_Hoed_AtAppStore

 

Hi Kaitlyn,

 

I believe what you're doing is the best possible via native Workfront reporting in that only the current Project Status is tracked (although technically, so is Project Previous Status) vs the "Project Status over time" you seek, so instead (as one option), suggest you consider setting up specific Hour Types (e.g. Scoping, Active, etc.) and teaching your team to choose the correct value as part of their time entry so you can in turn then summarize the hours by Project and by Hour Type.

 

Regards,

Doug

1 reply

Doug_Den_Hoed_AtAppStore
Community Advisor
Doug_Den_Hoed_AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
October 26, 2022

 

Hi Kaitlyn,

 

I believe what you're doing is the best possible via native Workfront reporting in that only the current Project Status is tracked (although technically, so is Project Previous Status) vs the "Project Status over time" you seek, so instead (as one option), suggest you consider setting up specific Hour Types (e.g. Scoping, Active, etc.) and teaching your team to choose the correct value as part of their time entry so you can in turn then summarize the hours by Project and by Hour Type.

 

Regards,

Doug