Report filter based on task name & status combination | Community
Skip to main content
Level 2
April 2, 2025
Solved

Report filter based on task name & status combination

  • April 2, 2025
  • 2 replies
  • 1315 views

Hello,

I need to create a report to filter out 2 specific tasks:

1) Task 1 - Asset Audit

2) Task 2 - Build

 

I want to filter out projects where Task 2 is in progress and Task 1 is not complete.

Task 1 - Actual end date is blank & Task 2 - Actual start end is not blank

 

When I tried "OR" in the filter, it either shows Task 1 / Task 2. I need to filter out the combination of task 1 + status & task 2 + status. 

 

Is there a way to create a filter for this combination?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

Starting a new thread to address clarifications made by the OP

 

EXISTS:a:$$OBJCODE=TASK
EXISTS:a:actualStartDate_Mod=notnull
EXISTS:a:name=build
EXISTS:a:name_Mod=cicontains
EXISTS:a:projectID=FIELD:projectID
EXISTS:b:$$OBJCODE=TASK
EXISTS:b:actualCompletionDate_Mod=isnull
EXISTS:b:name=asset audit
EXISTS:b:name_Mod=cicontains
EXISTS:b:projectID=FIELD:projectID

2 replies

Sven-iX
Community Advisor
Community Advisor
April 2, 2025

Why are you using an OR filter? Your definition above sounds like you want to AND the 2 conditions? 

Level 2
April 3, 2025

Hi @sven-ix That is correct. We need to use AND. However, with that I'm unable to specify for which task I need the completion date and which should have only start date.

 

Could you please suggest if there is a way I could do that?

 

Sven-iX
Community Advisor
Community Advisor
April 3, 2025

Pls share what type of report this is and your current filter

skyehansen
Community Advisor and Adobe Champion
skyehansenCommunity Advisor and Adobe ChampionAccepted solution
April 4, 2025

Starting a new thread to address clarifications made by the OP

 

EXISTS:a:$$OBJCODE=TASK
EXISTS:a:actualStartDate_Mod=notnull
EXISTS:a:name=build
EXISTS:a:name_Mod=cicontains
EXISTS:a:projectID=FIELD:projectID
EXISTS:b:$$OBJCODE=TASK
EXISTS:b:actualCompletionDate_Mod=isnull
EXISTS:b:name=asset audit
EXISTS:b:name_Mod=cicontains
EXISTS:b:projectID=FIELD:projectID

Level 2
April 7, 2025

This worked, thank you @skyehansen