Question

record delays in timeline

  • August 27, 2024
  • 1 reply
  • 431 views

is there a best method to record delays in a project? i'd like to start a project, and at the end look at how the project ended up and see that from the start of the project to the end, where the timeline shifted so its easy to report on who or what was the cause of the delay. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

skyehansen
Community Advisor and Adobe Champion
August 28, 2024

Have you investigated Workfront's "baseline" functionality?

https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/create-projects/create-baselines

 

This is usually where most people start.