Hello Community,

Is there a way to have a project task or a request close automatically once a proof has been approved?

 

We are getting Fusion implemented now so that may be an option, if needed.

 

Thank you,

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Richard_Le_

Hi,

 

Natively in Workfront, it's not possible to drive a task/request status change from a proof approval.

 

However, as you said, this can be achieved with Fusion. I believe that there is a pre-built Fusion template that you can use for exactly this use case, to save you having to build it from scratch. The template is called: Workfront Proof > Workfront - Task Update and Completion (if Approved) on Proof Decision. You can read more on this here.

 

Best Regards,

Rich.

 

 

2 replies

Richard_Le_Community AdvisorAccepted solution
Community Advisor
October 2, 2023

Hi,

 

Natively in Workfront, it's not possible to drive a task/request status change from a proof approval.

 

However, as you said, this can be achieved with Fusion. I believe that there is a pre-built Fusion template that you can use for exactly this use case, to save you having to build it from scratch. The template is called: Workfront Proof > Workfront - Task Update and Completion (if Approved) on Proof Decision. You can read more on this here.

 

Best Regards,

Rich.

 

 

Madalyn_Destafney
Community Advisor
Community Advisor
October 3, 2023

@richard_le_ is correct that you can't do this natively in WF. However, I do know it has been on the roadmap for some time now that we'll be able to tie proof and project statuses/task statuses together. Don't know details or ETA but it's in the works!