Project Progress Status and extending task duration time
I want to double check that extending task duration in a project that has fallen behind (Progress Status At Risk, Behind or Late and Project Condition At Risk or In Trouble) will never return the project to On Time-On Target. I’ve tested this a bit and found extending the duration dates will change the progress status and project condition to other levels, but the project never goes back to On Time-On Target. This makes sense to me since the progress status calculations are based on Estimated and Projected Completion Dates, which are system set. Are there project date situations that I missed in testing where changing task duration can reset an At Risk or Behind progress status to On Time?
Thanks