I’m trying to get the program name on a task report and it’s not working when using this text mode, what’s wrong with it?

displayname=Program Namelinkedname=project:program:namenamekey=view.relatedcolumnnamekeyargkey.0=project:program:namenamekeyargkey.1=project:program:namequerysort=project:program:namevaluefield=project:program:namevalueformat=customDataLabelsAsString
Best answer by NicoleM1

I got it! It was the value format! Don’t mind me over here talking to myself.

2 replies

NicoleM1
NicoleM1AuthorAccepted solution
Level 2
June 19, 2026

I got it! It was the value format! Don’t mind me over here talking to myself.

Level 2
June 19, 2026

displayname=Program Name
linkedname=project
namekey=view.relatedcolumn
namekeyargkey.0=project
namekeyargkey.1=program
querysort=project:program:name
textmode=true
valuefield=project:program:name
valueformat=HTML