Question
Predecessor Best Practices
Good Afternoon, I'll start by saying this is more of a Project Management Best Practices question, than it is tool focused.... but I realize there is a lot of PM process knowledge within this community so thank you in advance for reading & possibly providing your input! One project we have underway has well over 300 tasks. There is one 'critical' task which the PM has 13 predecessors assigned to it. He's of course articulated that all 13 things have to be done before this critical task can start. Seems to me, there has to be a better way.... I've confirmed none of the predecessor tasks are dependent on another. Grouping them under a parent task doesn't appear to be a reasonable option. Should I even be concerned with this; could it be reasonable to have so many predecessors? How to do you drive the conversation to clean this up, if it should be cleaned up? Thank you!! Jodi Biscevic GM Financial - International Operations