Predecessor Articulation - First Week of the Upcoming Month | Community
Skip to main content
DeborahLeigh123
Level 4
October 8, 2024
Question

Predecessor Articulation - First Week of the Upcoming Month

  • October 8, 2024
  • 1 reply
  • 415 views

My paid media team asked me an interesting question I wasn't sure how to answer. Can we set a reporting Task due the day of the first week of the Upcoming Month? If so, any suggestions? Thank You!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Madalyn_Destafney
Community Advisor
Community Advisor
October 9, 2024

Check out this article on lags/predecessors for help. Month isn't indicated in here but it could maybe work with 'm' instead of 'w' for weeks, or you could use a predecessor for 4 weeks. For example, if you want a task due the first Monday in 4 weeks after task 5, I think it would be 5fs+42w (42 is 4=4wks and 2=the # assigned to Monday in lags). 

If this helped you, please mark correct to help others : )