My nested tasks don't show up when I convert a request to a project. | Community
Skip to main content
MaryFox1967
Level 2
July 23, 2021
Question

My nested tasks don't show up when I convert a request to a project.

  • July 23, 2021
  • 1 reply
  • 562 views

We have templates for all of our projects. All the templates contain nested task sections that are associated with milestones. All of the sudden these no longer work when the template is made into a live project.

Anyone else have this happen?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

SamanthaIsin
Level 7
July 23, 2021

You need to sort by task number. Click the column header "#"

MaryFox1967
Level 2
July 26, 2021

Thanks! This must be a new change, in the past they always just showed up.