I have a request to change an existing Workfront proofing workflow. They want to switch the first and second stages. I didn't see a way to do that. Does anyone know if that is possible and if so, how to do it?

 

I was thinking about creating a new stage and then deleting the existing first stage. Would that affect any existing proofs that used this workflow?

 

Any other suggestions on how to accomplish this?

 

Marla

Best answer by RowvillBh1

It should not impact any closed/in progress proofs retroactively but will definitely impact any new proofs that you create using that template.

2 replies

RowvillBh1
RowvillBh1Accepted solution
Level 5
September 24, 2025

It should not impact any closed/in progress proofs retroactively but will definitely impact any new proofs that you create using that template.

VickiRose1
Level 2
October 1, 2025

Would like to have an enhancement made to allow stage re-orders. I'm in the same boat with a couple of workflows.