Question

Is there a way to pull in a *new* Updates column into the project task view so that a new update can be entered from the Project Task view? I see an option to pull in the Task "Last Note: Note Text" from the last update, but not to be able to key in

  • April 23, 2021
  • 1 reply
  • 604 views

Looking for a way for users to update their tasks without having to toggle back and forth between the project task list and drilling into the individual tasks to make an update at the task level.

I was also able to add a Notes column to the Project Task view, but notes keyed in here, do not transfer/save back to the task level updates.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Level 6
April 27, 2021

Hi Meg,

This is currently not possible, but there is an idea in the innovation lab that you can upvote:

https://one.workfront.com/s/idea/0870z000000PS80AAG/detail

MegSiAuthor
Level 2
April 27, 2021

Thanks @Sarah Nau‚ just voted this up!