Is there a way to distribute duration across a series of tasks that all have the same predecessor?

  • July 6, 2026
  • 3 replies
  • 57 views

Here is the scenario. I have 10 tasks all assigned to the same person. Each task has 2 days duration / 12 hours (6 hour day is my default). The tasks also have the same predecessor, so they all have the same planned completion date based on that shared predecessor.

Since they are all assigned to the same person and have the same due date, effectively the tasks pack 20 days’ work into only 2 days. The tasks will very quickly start showing as late.

Two ways I have previously solved this problem:
1. Make each of the tasks dependent on completing one another. Creates a hierarchy and distributes the time, but my end users want to be able to choose where to start on the tasks.

  1. Add artificially increasing durations so that the first task lasts 2 days, the second 4 days, etc. This includes the full time, but my end users don’t like inaccuracy of the durations.

Is there some way to have Workfront treat these tasks as if they were one task and set a due date that is realistic for the group of tasks without my having to make artificial changes ?

 

    Best answer by KellieGardner

    Task Tracking Mode doesn’t adjust the planned dates just how the tasks show as late. 

     

    What I’m hearing is this…

    • 10 tasks, same predecessor, same due date
    • Each task has only a 2-day duration 
    • 10 tasks × 2 days each = 20 days of total work needing to get done
    • Because they all share the same due date, that 20 days of work is effectively squeezed into a single 2-day window
    • One person, 10 tasks, same window = mathematically impossible to hit all 10 on time

    Option 1 - 

    Resource Leveling from the Gantt - Workfront will automatically push out the start/due dates of the conflicting tasks so the same person isn't scheduled on 10 things at once. It could help sequence them based on availability, rather than leaving them all crammed onto the same date Chart. However, this isn’t automatic, it has to be done manually on each project. Resource leveling also only applies to one project, so Adobe Workfront does not level resources across more than one project at a time

    https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/the-gantt-chart/gantt-chart-overview/level-resources-in-gantt

     

    Option 2 - if those tasks are truly not dependent on each other and can be done simultaneously. You could make the duration of all the tasks the full duration of that “part” of the project but leave the planned hours the same. If you stretch a task's duration from 2 days to 20 days while holding Planned Hours constant, Workfront spreads those same hours much thinner across each day. Example: if a task needs 16 hours of effort (2 days at 8 hrs/day), squeezed into a 2-day duration, that's 8 hrs/day of allocation. Stretch that same 16 hours across 20 days, and it's now just 0.8 hrs/day.

    3 replies

    Lyndsy-Denk
    Community Advisor
    Community Advisor
    July 7, 2026

    @ClintCl First, I have a question: Are you saying that you have planned hours totalling 20 days of work? In that case, it sounds like your durations need to be extended because of the physics of time. Am I misunderstanding?

    Assuming I’m misunderstanding, there are two things you might play with:

    1. Task Tracking Mode, specifically “Assume On Time” might benefit you. They don’t always work as loosely as you need, but can help.
    2. Scheduled-Start (sd) dependency looks like a Finish-Start but acts like a Finish-Finish. It’s possible this will relax the condition.
    ClintClAuthor
    Level 2
    July 7, 2026

    I have ten separate tasks that have the same due date because they all have a common predecessor. Each task is assigned 2 days duration but because the have the same due date, 20 days is effectively crammed into two days. All ten tasks are assigned to the same person which makes accomplishing all ten on-time impossible. I am looking for a way that Workfront can address this problem automatically rather than creating an artificial workflow that may not match up with how the work is actually accomplished or showing these tasks as late when it would have been impossible to complete them on-time based on how the tasks were created. That make sense? Sorry, it’s difficult to describe.

     

    Task Tracking Mode might work. Does “Assume on Time” adjust the Planned Completion Date automatically? That could be useful. We have pretty much used the default “User Must Update” exclusively.

     

     

    KellieGardner
    Community Advisor and Adobe Champion
    KellieGardnerCommunity Advisor and Adobe ChampionAccepted solution
    Community Advisor and Adobe Champion
    July 7, 2026

    Task Tracking Mode doesn’t adjust the planned dates just how the tasks show as late. 

     

    What I’m hearing is this…

    • 10 tasks, same predecessor, same due date
    • Each task has only a 2-day duration 
    • 10 tasks × 2 days each = 20 days of total work needing to get done
    • Because they all share the same due date, that 20 days of work is effectively squeezed into a single 2-day window
    • One person, 10 tasks, same window = mathematically impossible to hit all 10 on time

    Option 1 - 

    Resource Leveling from the Gantt - Workfront will automatically push out the start/due dates of the conflicting tasks so the same person isn't scheduled on 10 things at once. It could help sequence them based on availability, rather than leaving them all crammed onto the same date Chart. However, this isn’t automatic, it has to be done manually on each project. Resource leveling also only applies to one project, so Adobe Workfront does not level resources across more than one project at a time

    https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/the-gantt-chart/gantt-chart-overview/level-resources-in-gantt

     

    Option 2 - if those tasks are truly not dependent on each other and can be done simultaneously. You could make the duration of all the tasks the full duration of that “part” of the project but leave the planned hours the same. If you stretch a task's duration from 2 days to 20 days while holding Planned Hours constant, Workfront spreads those same hours much thinner across each day. Example: if a task needs 16 hours of effort (2 days at 8 hrs/day), squeezed into a 2-day duration, that's 8 hrs/day of allocation. Stretch that same 16 hours across 20 days, and it's now just 0.8 hrs/day.

    ClintClAuthor
    Level 2
    July 7, 2026

    I will try both of those suggestions. Thank you!