Is it possible to pull issue name into a task report when the issue is not converted but just moved to the task? | Community
Skip to main content
sydney_peterson
Level 3
November 7, 2024
Question

Is it possible to pull issue name into a task report when the issue is not converted but just moved to the task?

  • November 7, 2024
  • 2 replies
  • 630 views

I have a process where we are trying to see if an issue / request has been submitted that gets moved to tasks. I need the report to stay as a task report due to certain necessary filter criteria that I can't apply to an issue report. 

I need to reference if a task has an issue sitting on it - we don't convert the issues, we are just moving them. 

Is this possible to do in text mode? 

 

Here are some screenshots. Basically, I want the converted issue name, but it's not converted just moved. 

 

 
Updating Media

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

skyehansen
Community Advisor and Adobe Champion
November 9, 2024

I recommend you look into using collections in a report:

https://experienceleague.adobe.com/en/docs/workfront/using/reporting/reports/text-mode/reference-collections-report#reference-a-collection-in-the-view-of-a-report

 

You can literally steal this textmode straight off their page, as it should work for either task or project reports.

 

displayname=Issue Names
listdelimiter=<p>
listmethod=nested(issues).lists
textmode=true
type=iterate
valuefield=name
valueformat=HTML

Srinija_N
Level 7
November 11, 2024

May be you can still create a Issue report with 'Parent:name' as the group by and apply filters on the Parent and parent type.

If this helped to solve your problem, please mark it as 'solved' so others can also find the solution faster. Thanks!