Import Completed Project via Kickstart
We are attempting to import approx. 10,000 closed projects for historical reporting purposes. We added a summary task with Actual Start and Actual Completion dates identical to the Project Actual Start and Actual Completion dates. The project and task status are marked 'Complete' and the task is set to 100% complete.
Workfront gives us an error stating "Unable to complete operation for a project of status Complete". Is there a way around this?
Thanks for any suggestions you might be able to offer!