I am looking to provide an overview of our Programs showing the start and end date of each program.  The start date would be the planned start date of the project in that program with the earliest planned start date, and the end date would be the planned completion date of the project in that program with the latest planned completion date. 

 

Ideally, there would just be start and end columns that could be added to the view in the Programs section of Workfront, but those are not options.  Then we could view it in Gantt view.

 

Any ideas?

このトピックへの返信は締め切られました。

1 の返信

Kurt_Jones
Community Advisor
Community Advisor
October 3, 2023

IF you're on the Programs page you can create a unique view with just the columns you need, you can click the heading of Start On to sort from earliest to latest date and open you Gantt view; is this helpful?  This can be exported if needed.  But, yes, there isn't a reporting way of doing this, only from the Programs page.

 

 

 

Doug_Den_Hoed__AtAppStore
Community Advisor
Community Advisor
October 3, 2023

 

Hi @justin_charles,

 

In addition to the native suggestions @kurt_jones provided, I also invite you to consider our MarCom Gantt solution which lets you easily create, compare, sort, and adjust key Program level planning data including colorized Phase dates, Priority and % Complete. 

 

This video shows it in action, noting that the yellow toggles meet your exact requirement to show a single bar starting from the earliest planned start date (among all projects in the program) until the latest planned completion date (among all projects in the program).

 

Happy to chat further on email via doug.denhoed@atappstore.com

 

Regards,

Doug