How does Workfront hold users that cause bottleneck / delays accountable?
Hi,
I am trying to build a report to look at all completed tasks and to group them by their progress status. Apparently for completed tasks, the tasks progress status can only be either 'On Time' or 'Late'.
When it comes to tasks being completed late, there could be two potential reasons:
1. Their turn to complete the tasks reached them on time but they took longer time than the planned completion date causing the task to be completed late.
2. Their turn to complete the tasks reached them late. This is caused by the predecessor tasks were not completed on time and the bottleneck is causing delays towards the whole project.
We would love to only report the tasks that were completed late simply because of the assignee's own fault and not because of the bottleneck caused by the previous predecessor tasks. In summary, we would like to show report only for situation #1 above and to exclude the situation #2.
Anyone has any idea how can we do that? Any help is greatly appreciated.
Thank you!
Regards,
Arthur