Help With Calculation Predicting Total Hours Spent - Different from EAC

  • March 12, 2020
  • 1 reply
  • 1114 views
Hi All, I am new to WF, currently in the middle of my integration, planning to go live in the next 5 weeks. I am struggling with a calculation that is critical to project health. What I am looking for is a calculation that adds the total number of hours that have submitted against a project in the timesheet (Actual Hours) plus the hours that are still assigned to a resource or role in the future. It is fine if this calculation can only occur on the project level (in fact it may be better in my case). Almost 100% of our projects are a fixed budget with a fixed amount of hours, using this calculation will allow me to determine lots of other metrics including: True % complete (dividing actual hours by this calculation) Actual Effective Bill Rate (dividing the $ Budget by this calculation) % over or under hours budget Etc. Ideally, the calculation would be: Actual Hours - From the start of the project through the end of the previous week PLUS Scheduled Hours - Current week until the end of the project I can live with it if the future scheduled hours need to use today as the start point. The EAC calculation comes close to doing this, but too much is dependant on the team actually updating the % complete on the task level, which I assume will not actually happen without lots of prodding. Kris Murphy Bluecadet
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Level 3
May 4, 2020

Kris,

If I am understanding this correctly you are looking for the hours remaining for the project. So Planned Hours for the project minus the Actual Hours for the project. I worded it differently but think it is the same thing. Is that correct? If that is the case then below text mode on a Project Report should give you what you are looking for.

displayname=Remaining Hours textmode=true valueexpression=CONCAT(DIV(SUB({workRequired},{actualWorkRequired}),60)," Hours") valueformat=HTML

KrisMuAuthor
Level 3
May 4, 2020

@Adam Millet - inactive‚

Thanks for the reply. I'm not sure if that 100% gets me to what I am looking for since (I think) it is possible to have more hours projected at completion for a task than what is represented in the plan number.

For instance, there is a task spanning two months with 100 planned hours (evenly broken out for each month). At the end of the first month, the team member has entered 100 hours towards the task, but there are still 50 hours scheduled for the next month (the task is going over budget).

Using your math, I think it would tell me that there were 0 hours remaining to be worked since it would be subtracted actual hours from plan. But there are 50 hours next month that still need to be worked, so the total amount of time it would take to complete the task is 150 hours.

Does that make sense, is there a solve for this? We are not up and running on Workfront yet (still in integration), so still learning the ins and outs.

Thanks.

Level 3
May 6, 2020

Kris,

I have been testing this the past few days and cannot find a way to accomplish this. The problem that I am running into to get this to work is there is not a way to break out the planned hours evenly through the month that would be consistent. However, there is a budgeting tool in Workfront that is already built that may help with this. Here is more info on this tool.