Help with a calculated field
I won't get into details around why it's needed but we are looking to do a calculated field in a task view that would show us the % complete Workfront thinks a task should be at. For these projects we use Planned Hours to calculate our % Complete
Ideally it would look similar to this
| Name | Duration | Pln Hrs | Planned Start Date | Planned Completion Date | % Complete (native Workfront field that currently exists and allows updates) | Calculated field to show what % should be |
| Task 1 | 10 days | 40 Hours | xx | xx | 30.00% | 50% |
| Task 2 | 100 days | 50 Hours | xx | xx | 25.00% | 75% |
| Task 3 | 5 Days | 5 Hours | xx | xx | 10.00% | 5% |