Question
Frozen Calculated Custom Field
Does anyone have a workaround or a fix for this issue:
One of our teams wants to add a calculated custom field on all their projects. The field would be Cycle Time and the calculation is the duration of the project from planned start date to $$TODAY and it subtracts any On Hold time.
The problem is that the calculation only updates whenever someone update the custom form or edits the project details. If we don't make any updates to the project for a day or so, the calc will stay frozen since the last update thus showing incorrect information.
Is there any way to automate the refresh of calculated custom fields? Or any ideas to easily refresh that calc on a bunch of projects on a routine basis?
I believe this idea exchange from 2017 talks about this issue: https://experience.workfront.com/s/idea/0870z000000PSEkAAO/detail Denver Lemont Cardinal Health