Fixed Dates in a Workfront Template
I have a template that utilizes fixed dates for the task constraints. When I create a project with the template, no matter what the start date of the project is, my tasks are all defaulting to decimal durations.
If I create a project today with a start date of tomorrow at 9AM. The tasks were all created using that as the start date and time, but the end dates are defaulting to 2 pm resulting in less than full days.