We track the number of projects for KPI. Is there a way to filter for when a project status is changed to complete  so we know the date that was done.

    1 reply

    ElvinM
    Level 2
    February 13, 2026

    If I’m understanding the question correctly, I think you can use the Actual Completion date to get basically the answer you’re looking for.

    djsluzasAuthor
    Level 1
    February 13, 2026

    It does get me the basics but if we would need to change all the open tasks prior to the status change. This was not done in the past.